Wednesday, January 7, 2009

IT GOING TO COST US ABOUT 6.6ML

In order to bring close the service of water to the residents of Mboma road it requires us to raise about 6.6 ml out of connection fees. This is a cost of main line construction, Wo Can we, Yes we can. The costs required cover only 308 m, that is 78m from Reserve Tank to Col Masero and 230m from Col Masero to Kitimoto.

As I went through I realise we are about 20 residents and incase we devide the sum among ourself we are required to contribute almost about 330,000 mind you is not an exactly figure. Let advise each other what are going to do

Ha ha haaaa

We real need water at Salasala, lack is for those who are already connected but Inshallah things will be OK.